Marion Outdoor Swimming Centre Master Plan
Aquatics
The City of Marion Council engaged Tredwell Management Services, Donovan Payne Architects and RMP & Associates to develop a Master Plan for the Marion Outdoor Swimming Centre.
The Master Plan was developed over the course of 4 key stages.
Stage 1: Project start-up, site appraisal & literature review
Stage 2: Consultation & Background Report
Stage 3: Options development, Draft Master Plan & Initial Feasibility Report
Stage 4: Final Master Plan
The project delivered three preliminary master plan options with cost estimates which were subject to comprehensive consultation with stakeholders. Engagement with Elected Members, staff and the community determined the preferred option which was further refined for the final Master Plan.